| 
		 
		  | 
	|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 
		 The Business Case for OR&A™ 
		
		Introduction - Will the Project be completed without harm to anyone involved? - Will the total cost be within 25% of the approved budget? - Will the Project be completed on schedule? - Will the completed asset deliver what was promised at FID? 
		
		Data from a large number of mega 
		projects showed that more than 65% of them were judged as having failed 
		on one or more of the criteria used and many exhibited continuing 
		operational problems into the 2nd and 3rd years after start-up. The solution to this problem is to ensure the requirements of the Owner/Operator are addressed during the conceptual, design and construction processes to ensure the Operability and Maintainability (and therefore the viability) of the asset is achieved. This is done using a robust Operations Readiness & Assurance process. 
		
		Until the creation of the  
		OR&A™ 
		Solution, there were two main 
		obstacles to Companies wishing to use  OR&A™ 
		on their projects, these were cost and availability. A further 
		complication was the lack of the ability to explain how using  OR&A™ 
		would benefit the Project (and subsequently the Asset) and how this 
		could ever be cost effective (or reduce costs). 
		
		Business Case However, the framework below outlines such a Business Case which illustrates how losses from failing to deploy OR&A could amount to some 9% of Asset Value over the first 5 years of operation. Furthermore, the example below also illustrates how deploying OR&A™ can provide a return of 15:1 on the original investment over those same 5 years. The calculations used here are extrapolated from a paper entitled 'Justification for Maintenance & Reliability Readiness' by Murray Macza of MRG Reliability Consulting, who made a number of basic assumptions using typical industry specific benchmark data and baseline information on operability, maintainability and availability to develop the figures shown below. 
 
 Calculation of Benefits from using OR&A™ 
		
		Reduced Maintenance Costs - Reductions in the need for re-work during the EXECUTE phase; - Operations contributions to the design process (operability); - Reduction in Spare Parts requirements (improved maintainability); - Reductions in Project manpower costs due to embedding Operations personnel in Project. Typically, savings of between 2.5% and 4% (approximately $20m per year) can be realized. 
		
		Reduced Spare Parts Costs - Rationalisation of the spare parts inventory for the first 2yrs operation; - Commensurate reduction in Supply Chain costs for replacements; - Commensurate reduction in logistics (warehousing/labour) costs; Typically, initial savings of between 0.5% and 1.5% (approximately $10m) on CAPEX and a reduction in OPEX of $2.5m per year can be realized. 
		
		Improved Production 
		Performance It is not unreasonable to assume then, that implementing OR&A would improve operability (production output) by some 5% in the first year of production and that this would typically equate to approximately $3.5m, calculated as follows: 100,000 barrels/day x 347** days x 5% x $40 = $69.4m (**365 days x 95% plant availability = 347 days) Assuming production is deferred rather than lost, at an interest rate of 5%, such an improvement would save some $3.5m per year in interest payments alone. Further benefits - Reduced Energy Consumption from better maintained equipment (typically 3% - 14% lower); - Reduced downtime for scheduled, unscheduled and breakdown maintenance (typically 30% to 60% lower); - Reduced waste through improved quality of product (typically 5% - 15%); However, because these costs vary from business to business, these savings cannot be quantified and are therefore not included in the calculations. 
 
		
		Conclusion: If the NPV calculated above were taken to be losses (due to a failure to deploy OR&A) this equates to almost 10% of lost value over the first 5 years (2% per year). Another way of looking at the cost of OR&A is to consider the actual cost in terms of lost production revenue: Total Estimated Cost of doing OR&A (typical) = $5.5m ...... or just 32 hours lost Production Revenue  | 
	|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 
		 © OR&A™  |